The BQE Plan's Only Permanent Mark on Brooklyn Heights Is a Corner of Squibb Park

October 22, 2026

Walk Furman Street under the triple cantilever and you can see the rusted rebar and cracked concrete holding up the structure, as Gothamist photographed it in August. The cantilever opened in 1954 with a 50-year design life. At its October 6 virtual Q&A, DOT chief strategy officer Tiffany-Ann Taylor said it is now "beyond its design life," according to Pineapple Street.

The city's answer is the BQE Central rehabilitation. It would keep the highway at two lanes, repair the structure in place and extend its service life by about 40 years. DOT estimates the cost at $3.5 billion to $4 billion, and $1.6 billion of that is currently allocated in the City Capital Plan. Most coverage has focused on the Promenade. The project's footprint on Brooklyn Heights' public space is spread wider than that. Its one permanent loss sits at the north end, by Columbia Heights. The parts that last a decade or more are officially called temporary, and their study is being defined this fall.

The Change That Stays After 2040

At the October 6 session, project engineer Matt Kusy said a corner of Squibb Park would be permanently taken to make room for a rebuilt overpass near Columbia Heights. Pineapple Street reported that he called it "minor permanent alienation." DOT's Draft Scope of Work, dated October 2, describes the work. The Columbia Heights overpass would get a new superstructure, and its north abutment would be relocated and rebuilt.

Three nearby spaces sit beside that permanent change and would be disrupted for years:

  • Harry Chapin Playground, at Columbia Heights and Middagh Street, would be removed during construction and rebuilt afterward.
  • Squibb Park would be temporarily affected beyond the corner it loses for good.
  • Hillside Dog Park is also on DOT's list of spaces temporarily affected.

Parkland in New York can't be used for anything else, even briefly, unless Albany approves it. So state lawmakers would need to sign off on both the temporary use of these parks and the permanent loss at Squibb Park. According to the timeline DOT presented on October 6, alienation legislation would be drafted in late 2027 and passed in 2028. That gives the north end of the neighborhood a defined point in the process where these park questions get settled.

The Promenade Closes in Pieces

The Promenade is part of the rehabilitation. When the plan was announced, Transportation Commissioner Mike Flynn said construction would require closing sections of it, according to Gothamist. Officials also pledged to keep at least one portion open at all times. At the October 6 Q&A, Kusy described the method. Work would move along the Promenade several spans at a time, either north to south or south to north. Taylor put the commitment this way, as reported by Pineapple Street:

"As long as it is safe and feasible throughout the construction life of this project, we are maintaining access to the promenade. We have heard folks over and over that it is a really important open space to the community and to visitors alike, so we have committed to that."

DOT's project page uses similar language. It says access to "portions of the Promenade" will be maintained at all times, "to the extent feasible." DOT has not published which sections close first, for how long, or in what order. Gothamist pointed to the 2018 plan as context: that proposal would have closed the Promenade for six years, and the de Blasio administration dropped it.

DOT's published schedule puts the start of construction in 2029, so no construction closure is planned before then. The cantilever is still carrying traffic in its current two-lane setup. DOT says the structure is safe today because of three things: targeted interim repairs, enforcement against overweight trucks, and the cut to two lanes. The Draft Scope adds that the 2021 lane reduction lowered traffic loads but did not fix the underlying deterioration of the material.

Two Temporary Highways, One Below the Promenade

The span-by-span approach depends on keeping traffic moving somewhere else. DOT's answer is a two-level bypass over Furman Street, no higher than the existing Queens-bound level. North of Columbia Heights, a second bypass would carry Queens-bound traffic over the existing BQE and the Brooklyn Bridge approach. DOT says it is still reviewing other design options. Whatever the final design, the structures would come down when construction ends. Flynn told Gothamist the temporary roadway would be "tucked out of view" from the Promenade.

Brooklyn Bridge Park sits right next to that Furman Street alignment. On October 1, DOT spokesperson Will Livingston told Streetsblog, "We are not planning for any impacts to Brooklyn Bridge Park through construction." The Draft Scope still lists Brooklyn Bridge Park and the Promenade among the open spaces whose direct effects will be studied. Where relevant, that study includes potential increases in noise and air pollutants. DOT doesn't expect impacts, and the environmental review will test that expectation.

Neighborhood organizations reacted to the bypass with their own concerns. Lara Birnback, executive director of the Brooklyn Heights Association, told Brooklyn Paper she was glad the footprint would not expand and the highway would stay at two lanes. She also said the group has "some concerns around the idea of the bypass highway," a concept she noted had been rejected before. Kelly Carroll, executive director of the Atlantic Avenue BID, called the plan "a missed opportunity." She pointed to the Atlantic Avenue interchange, which the plan leaves unchanged, and to families crossing under the BQE to reach Brooklyn Bridge Park. In a joint statement, State Sen. Andrew Gounardes, Assemblymember Jo Anne Simon and Councilmember Lincoln Restler called for transparent engagement, better air quality and new connections to Brooklyn Bridge Park.

Former DOT Commissioner Hank Gutman went further at a September 17 Brooklyn Marine Terminal board meeting, according to Streetsblog. He argued that a temporary closure of the Atlantic Avenue on-ramp during repairs would let the city study real-world traffic effects. Taylor responded at that meeting. She cited the need to be "really balanced" with the federal government and called the current design "the most conservative proposal put forward for now." The city plans to seek no federal funds for this city-owned segment.

A Decade of "Temporary"

At the October 6 Q&A, Taylor acknowledged the objections to the word "temporary." According to Pineapple Street, she said, "In this instance, it's a long time temporary." She also said the 10-year estimate does not account for possible delays from land use review or lawsuits. Here is the schedule as currently published. DOT labels all of it preliminary.

Milestone Current target Source
Public scoping and comments October to November 2026 DOT Q&A deck
Final Scope of Work Early spring 2027 DOT Q&A deck
Draft Environmental Impact Statement Fall 2027 DOT Q&A deck
ULURP vote, alienation legislation, Final EIS 2028 DOT Q&A deck
Construction begins 2029 DOT project page
Traffic moves onto temporary bypasses Between 2030 and 2032 Brooklyn Eagle
Triple cantilever rehabilitation begins 2032 Brooklyn Eagle, Gothamist
Bypass removed, restored highway reopens By 2040 Gothamist, DOT

The Brooklyn Eagle reported that the full move onto the bypass is projected for the first half of 2032.

The north end gets one more layer on top of this. At the October 6 session, Pineapple Street reported, residents raised the overlap with two other projects already underway along the waterfront: the Watchtower conversion at 25–30 Columbia Heights and the Brooklyn Marine Terminal redevelopment. Taken together, these could mean years of overlapping construction from Dumbo to Red Hook. A household near Old Fulton Street or the top of Columbia Heights could be living beside all three at once.

Why This Fall Sets the Terms

Construction is years away, but the environmental review it depends on is already open. Public scoping is the step where anyone can comment on which impacts the Environmental Impact Statement should study, which topics it covers and how far its study areas reach. DOT will then publish a Final Scope that responds to those comments. The Draft Scope already says that possible temporary narrowing or closure of streets, sidewalks and crosswalks during construction is a subject for the EIS. The span sequence on the Promenade, the playground's absence and access to Furman Street will all be studied under whatever scope comes out of this window.

The remaining dates, as of publication:

  1. Thursday, October 29, 6 to 8 p.m. DOT information session at Brooklyn Borough Hall, 209 Joralemon Street. Advance registration is required.
  2. Thursday, November 5. Deadline to request language interpretation for the virtual scoping meeting.
  3. Tuesday, November 10, 6:30 to 8:30 p.m. In-person CEQR scoping meeting at New York City College of Technology, 300 Jay Street, as listed in DOT's Positive Declaration. DOT's project page still lists the venue as "to be announced," so check before you go.
  4. Thursday, November 12, 6:30 to 8:30 p.m. Virtual CEQR scoping meeting on Zoom. Registration is required.
  5. Monday, November 23. Last day for written comments. You can submit them through DOT's online form, which caps comments at 512 characters, by email to [email protected], or by mail to the BQE Central Project Team at 55 Water Street.

Full materials, including the Draft Scope and the bypass renderings, are on DOT's BQE Central project page.

Owners along Columbia Heights, Furman Street and the blocks near Squibb Park can expect buyers to ask about this timeline for years. If you're weighing a sale or a purchase that a 2029 to 2040 construction schedule could affect, The Heard Khedr Team can go through the BQE timeline with you block by block. Book a Home Valuation and we'll show you what nearby buyers are paying now.